ATC Receives Approval from PSC for Transmission Line

ATC Receives Approval from PSC for Transmission Line

On January 12th, American Transmission Company received approval from the Public Service
Commission of Wisconsin to construct an approximately 4.2 mile, 345,000-volt Riverside
Transmission Line Project. The project will consist of a double-circuit transmission line from a
planned new substation near the Alliant Energy West Riverside Energy Center to an existing
345-kV transmission line in the Town of Beloit.

The line is needed to connect the expanded West Riverside Energy Center to the electric
transmission grid. The West Riverside Energy Center will include a natural gas-fueled
generating station with an integrated solar installation.

“The ordered route is made up of segments from the two routes that ATC submitted to the PSC,”
said ATC Project Manager Mark Sanzenbacher. “The anticipated project cost is approximately
$42 million.”

The planned in-service date of the line is 2019.